Math, asked by hassan2677, 1 year ago

Twelve men take 6 hours to finish a piece of work. After the 12 men have worked for 1 hour, the contractor decides to call in 8 more men. How many more hours would 20 men take to complete the remaining work?

Answers

Answered by Advik007
14

The answer is 3 hours.


This is a simple inverse proportion question.


So, understand, if 12 men can finish work in 6 hours, they can do 1/6th of the work in 1 hour.


So, in 1 hour, work done by 12 men = 1/6.

Work remaining = 5/6.


12 men ----- 6 hrs

20 men ----- x


x = 12*6/20

x = 18/5 hrs


That means 20 men can finish 5/18 of work in 1 hour.


Thus time to be taken by the 20 men to finish work = 5/18 * y = 5/6


y = 3 hours.


The answer is 3 hours.


Advik007: Please mark me down as the Brainliest if this was helpful!
Answered by TooFree
17

12 men takes 6 hours to finish a piece of work

⇒ 1 hour = 1/6 of the work


Find the amount of work left after 1 hour

Work left = 1 - 1/6  = 5/6


Find the number of men available after 8 more joined in :

Total number of men = 12 + 8 = 20


Find the number of hours needed for 20 men to finish the work:

12 men = 6 hours

1 man = 12 x 6 = 72 hours

20 men = 72 ÷ 20 = 3.6 hours


Find the amount of work 20 men can do in 1 hour:

20 men can complete the work in 3.6 hours

⇒ 1 hour = 1 ÷ 3.6 = 5/18 of the work


Find the number of days needed to complete the remaining work:

Number of days = 5/6 ÷ 5/18 = 3 days


Answer: The 20 men will need 3 more days to finish the work.


TheLostMonk: Nice Answer !
Similar questions