twelve women working 7 hours a day can finish a piece of work in 8 days . how many hours a day must 16 women work in order to finish the job in 4days women work in order to

Answers

Answered by Anonymous
3

Answer:

The job takes 672 woman/hours (12 * 7 * 8)

16 * h * 7 = 672

112h = 672

h = 6

Answered by rashmigarai1985
1

Step-by-step explanation:

The job takes 672 womans/hours (12*7*8) 16*h*7 =672 112hr =672 h=6.