Twelven men can complete a job in 15 days. how many men will be requred to finish the work in 9 days
Answers
Answered by
1
Answer:
Free Fire only
Step-by-step explanation:
free fire sahb ka baap aha only free fire
Answered by
0
Answer:
20 days
Step-by-step explanation:
12 men take 15 days to complete a job. Then time taken by 1 men = 15 into 12.
=180 days.
Now we have the time taken by "x" number of men = 9 days.
Number of men = 15 into 12/9
= 180/9
=20 men.
Please mark it as brainliest.