twenty two men can complete a piece of work in 17 days.They work for 2days.How many more man should be employed so as to complete the work in another 10 days

Answers

Answered by CoruscatingGarçon
13

Answer:11


Step-by-step explanation:

Work done by 22 men in two days=2/17.

Remaining work is 1-2/17=15/17.

This 15/17 work have to be done in 10 days.

So from unitary method we get 22×15/10=33.

So the extra men needed is 33-22=11.hence answer is 11