Twenty workers can finish a piece of work in35 days .After how many days should 4 worlers leave the job so that the work is completed in40 days
Answers
Answered by
2
Answer:
15 Days
Please mark the answer as "The Brainliest answer" if you like it
Step-by-step explanation:
Let say after x days 4 workers left
then for x days 20 workers worked
for 40-x days 16 (20-4) workers worked
20*35 = 20*x + 16*(40-x)
700 = 20x + 640 -16x
60 = 4x
x = 15
x = 15