Math, asked by ch6917277, 7 months ago

Two class rooms are to be built in a school and planned that 8 masons and labours shall complete them is 20 daya, if the number of workers is increased up to 10, how many days will be taken in the completion of work?​

Answers

Answered by akashrim18
0

Answer:

16 days

Step-by-step explanation:

8 labours =20 days

1 labour = 20×8=160 days

then 10 labour should complete the same work in = 160/10=16days

Similar questions