Two content managers can complete developing questions for a module in 18 days

Answers

Answered by angel881
4

Answer:

Discover more every day. Assessments ... To Prepare for this exam complete the Excel Module 3 SAM Training. .... It is 75 minutes, 18 -22 questions, and costs $75 USD. Inpatient ...

Answered by Anonymous
2

Step-by-step explanation:

Two content Managers can complete developing questions for a module in 18

days.

=> one manager will take 18 * 2 = 36 Days to complete module

=> one manger one day work = 1/36

Work done in 7 Days = 7/18

Remaining work = 1 - 7/18 = 11/18

10 Interns join so total Man power available = 2 + 10 = 12

12 People one day work = 12 * 1/36 = 1/3

Number of days required = (11/18)/(1/3) = 11/6 ≈ 2 Days