Math, asked by darshith69, 3 months ago

Two friends are assigned to complete a job, where one friend can complete the job in half the time of other friend, so in how many days will they will complete the job, working together, if the slower one completes the job in 12 days ?

Answers

Answered by bson
1

Answer:

4 days

Step-by-step explanation:

s is slower, f is faster

total work = time × efficiency = 1×12 =12

no. of days taken by f

= total work/ efficiency of f

= 12/2 =6 days

efficiency of S+F = 1+2 =3

no. of days taken by s+f = 12/3 =4 days