two labour A and B can harvest field in 18 days they worked together for 8 days and then we could and alien finish the work in 15 days how long would each of them take the finish the harvesting work separately
Answers
Let A takes 'x' time to complete the work alone.
So, one day work of A = 1/x
And,
Let B takes 'y' time to complete the work alone.
So, one day work of B = 1/y
One day work of both A and B when they work together = 1/8
Now,
⇒ 1/x + 1/y = 1/8
They work together for 6 days and A left. That means 6/8 work had already been completed.
So, remaining work = 1 - 6/8
= 2/8
= 1/4
So, 1/4th part of total work is still remaining and B finished this 1/4th part in 6 days.
⇒ 6(1/y) = 1/4
⇒ 6/y = 1/4
⇒ y = 24
Hence B will take 24 days to complete the work alone.
Now,
Substituting the value of y = 24, we can have the value of x.
1/x + 1/y = 1/8
⇒ 1/x + 1/24 = 1/8
⇒ 1/x = 1/8 - 1/24
⇒ 1/x = 2/24
⇒ 1/x = 1/12
⇒ x = 12
So, A will take 12 days to complete the work alone.