Math, asked by ricardo07, 11 months ago

two men and 17 women can do a piece of work in 4 days it is done by 4 men and 4 women in 3 days how long would it take for one man and one woman to do the work​

Answers

Answered by anika94
1

4 day in work =2 men + 17 women

1 day in work = 4 ( 2 men + 17 women )

= 8 men +68 women

3 day in a work= 4 men +4 women

1 day in a Work =3 (4 men+ 4 women )

. 12 men + 12 women

8 men + 68 women= 12 man+12 women

68 women _12 men= 12 man_8 man

56 women =4 man

14 women =1 man

2man+17 women =(2×14+17)=

45 women

1 men +1 women = 1 ×14 +1 =15 women

45 women do one work =4 days

1 .....................................=4 ×45=180 days

15...................................=180/15=12 days

one man and one women =12 days