Two men can do a price of work in 3 day & 6 days respectively .if they work together , in how many days will they finished the work ?

Answers

Answered by anuhoney
0
For one day, first men do 1/3 work
For one day, second men do 1/6 work
combine both =1/3+1/6
=1/2
For one day they will do together 1/2 of work
Total work can be done in 2 days

They can finish the work in 2 days