Two men complete a work in 50 days. five women complete it in 25 days. one man and one woman will complete the work in _ days.

Answers

Answered by ArchitectSethRollins
8
Hi friend
----------------
Your answer
---------------------

Two men complete a work in = 50 days

Time taken by one man to do the work = 50×2 = 100 days

Work done by the man in one day = 1/100 the work

Time taken by 5 women to complete the work = 25 days

Time taken by one woman to do the work= 25×5 = 125 days

Work done by one woman in one day = 1/125 the work


Work done by one man and one woman to in one day = (1/100 + 1/125) the work
=> (9/500) the work

So,
------
Time taken by them to finish the work = (1 ÷ 9/500) days => 500/9 days => 55.5 days

HOPE IT HELPS