Two men take 12 days to complete a job. How many days will 12 men take to

complete the same job?​

Answers

Answered by prasanthikuchipudi
0

Answer:

2 days

Step-by-step explanation:

we know,

work=men*hours*time

Given,

Two men take 12 days to complete a job.

2 men*12 days=1 work

How many days will 12 men take to  complete the same job?​

let the days be x

x days*12 men=1 work

if work is same then,

2*12=x*12

x=2 days

Answered by sohan83sharma
0

Answer:

May this helpful mark me brainless