Math, asked by honeydrall9900, 11 months ago

Two people can complete work in 4 days, 1st person can complete in 12 days.The second can do it in how many days

Answers

Answered by mukesh777
0

second person do work required day = reciprocal of ( 1/ 4 - 1/12 )

= reciprocal of 2/12

= 6

in 6 days

Similar questions