Two people P and Q can finish a piece of work in
12 days. P alone can finish it in 30 days. In how many
days can Q alone complete the job?
Answers
Answered by
3
Answer:
30 and 12 l.c.m is 60
p efficiency 2
p and q efficiency 5
substract 2 from 5
q efficiency 3
work 60
so 60 /3 = 20