Math, asked by Anonymous, 7 months ago

Two persons A and B could finish a work in p days. They worked together for q days. Then A was called off, and the remaining work was completed by B in r days. In how many days could each of them do it?​

Answers

Answered by ExᴏᴛɪᴄExᴘʟᴏʀᴇƦ
14

\huge\sf\pink{Answer}

\sf \dfrac{1}{x} = \dfrac{r-p+q}{pr}

\sf \dfrac{1}{y} = \dfrac{p-q}{pr}

━━━━━━━━━━━━━

\huge\sf\blue{Given}

✭ Two persons A & B could complete a work in p days

✭ Number of days they worked together is q

✭ After that A was off and B apne had to complete the work, he took r days

━━━━━━━━━━━━━

\huge\sf\gray{To \:Find}

◈ Number of days taken be reach of them?

━━━━━━━━━━━━━

\huge\sf\purple{Steps}

\large\underline{\underline{\sf Let}}

◕ Work done by A be x

◕ Work done by B be y

\underline{\sf As \ Per \ the \ Question}

Both A & B work for a time p so then in one day,

\sf \dfrac{1}{x}+\dfrac{1}{y} = \dfrac{1}{p} \:\:\: -eq(1)

So if they work for q days,then they both will complete,

»» \sf q\times \dfrac{1}{p}

»» \sf \dfrac{q}{p}

If total work was 1

\sf 1-\dfrac{q}{p}

\sf \dfrac{p-q}{p}

Given that B works for r days, then work done by B will be,

\sf \dfrac{1}{y} = \dfrac{\dfrac{p-q}{p}}{r}

\sf \dfrac{1}{y} = \dfrac{p-q}{p\times r}

\sf \red{\dfrac{1}{y} = \dfrac{p-q}{pr}}

From eq(1)

\sf \dfrac{1}{x} = \dfrac{1}{p} - \dfrac{p-q}{pr}

\sf \dfrac{1}{x} = \dfrac{r-(p-q)}{pr}

\sf \orange{\dfrac{1}{x} = \dfrac{r-p+q}{pr}}

━━━━━━━━━━━━━━━━━━

Similar questions