Two persons A and B could finish a work in p days. They worked together for q days. Then A was called off, and the remaining work was completed by B in r days. In how many days could each of them do it?
Answers
Answered by
14
☞
☞
━━━━━━━━━━━━━
✭ Two persons A & B could complete a work in p days
✭ Number of days they worked together is q
✭ After that A was off and B apne had to complete the work, he took r days
━━━━━━━━━━━━━
◈ Number of days taken be reach of them?
━━━━━━━━━━━━━
◕ Work done by A be x
◕ Work done by B be y
☯
Both A & B work for a time p so then in one day,
≫
So if they work for q days,then they both will complete,
»»
»»
If total work was 1
➳
➳
Given that B works for r days, then work done by B will be,
➝
➝
➝
From eq(1)
➝
➝
➝
━━━━━━━━━━━━━━━━━━
Similar questions