Math, asked by chandnipatel2030, 3 months ago

Two persons can paint a wall in 12 days. The first
person works alone, paints of the wall in 10 days
1/3
and then he leaves. If the second person was to paint
the remaining wall alone, in how many days will he
complete the job?

Answers

Answered by armaanmnair
1

Answer:

So, in 1 day he will complete part of the wall. So, working together in 1 day they will do part of the wall. So, the whole wall will be painted in days. ⇒ x = 13.33 days.

Answered by rahil27february
1

Answer:

Answer would be 8

Step-by-step explanation:

2 persons - 12 days

1 person - 10 days -1/3 work

2/3 work is left stll

2nd person 2/3 work

1 st person days to do work - 12/3 equals to 4

2nd person days to work - 12-4 equals to 8

Mark me as brainliest please !!!!!