. Two persons could fit new windows in a house in 3 days.
(1) One of the persons fell ill before the work started. How long would the job
take now?
(ii) How many persons would be needed to fit the windows in one day?​

Answers

Answered by RajSrivastava1
6

Answer:

6 persons

Step-by-step explanation:

Less the number of days, more will be the number of persons required to fit all the windows. Hence, this is a case of inverse proportion. Hence, 6 persons are required to fit all the windows in one day