. Two persons could fit new windows in a house in 3 days.
(i) One of the persons fell ill before the work started. How long would the job take now?
(ii) How many persons would be needed to fit the windows in one day?
Answers
Answered by
3
Answer:
1) one person take 6 days
2) in one day for the fixing of window required person is 6 nos
Step-by-step explanation:
both person work together for complete the work it takes 3 days
then single person can complete half in 3 days
it takes 6 days to complete the work
in a one day complete the we require 6 person
Answered by
1
i) x1y1=x2y2
2 X 3 = 1 X y2
Y2 = = 6
2 X 3
1
Hence, the required number of days = 6