two persons could fit new windows in a house in 3 days one of the person fell it before the work started how long would the job take now.
Answers
Answered by
1
Answer:
Less the number of days, more will be the number of persons required to fit all the windows. Hence, this is a case of inverse proportion. Hence, 6 persons are required to fit all the windows in one day.06-Sep-2017
Answered by
0
Answer:
6 days
Step-by-step explanation:
because it take double time to fit it