Two tailors P and Q earn ₹350 and ₹450 per day respectively. Tailor P can stitch 6 shirts and 3 trousers while tailor Q can stitch 7 shirts and 3 trousers per day. How many days should each of them work, if it is desired to produce at least 51 shirts and 24 trousers at a minimum labour cost?

Answers

Answered by shubhammohnani
0
this was simple...u got it?
Attachments:
Answered by amitnrw
1

Answer:

P need to work 5 days & Q need to work 3 days to have minimum labour cost

Step-by-step explanation:

Two tailors P and Q earn ₹350 and ₹450 per day respectively. Tailor P can stitch 6 shirts and 3 trousers while tailor Q can stitch 7 shirts and 3 trousers per day. How many days should each of them work, if it is desired to produce at least 51 shirts and 24 trousers at a minimum labour cost?

P - 6 S  + 3T

Q - 7S +  3T

at least 51 shirts and 24 trousers so below are the cases

P    Q    Shirts & trousers      Cost

9    0     54  & 27                   Rs 3150

8    1      55  & 27                   Rs 3250

7    2      56  & 27                   Rs 3350

6    3      57  & 27                   Rs 3450

5    3      51  & 24                    Rs 3100

4    4       52 & 24                   Rs 3200

3    5       53  & 24                  Rs 3300

2     6      54 & 24                   Rs 3400

1      7       55  & 24                 Rs 3500

0     8       56   & 24                Rs 3600

We can see that minimum labour cost = Rs 3100

P need to work 5 days & Q need to work 3 days to have minimum labour cost