Math, asked by pasana1660, 1 year ago

Two workers a and b are employed to do a cleanup work. a can clean the whole area in 800 days. he works for 100 days and leaves the work. b working alone finishes the remaining work in 350 days. if a and b would have worked for the whole time, how much time would it have taken to complete the work?

Answers

Answered by Stephen111
1
no.days took to complete the work a=800
no.days a worked=100


remaining a=700
no.day to b=350
700a--------------------350b
800a--------------------x
x×700a=350b×800a
x=400
let total land =y
per one day a=y/800
per one day b=y/400
each day=(y/800)+(y/400)
=3y/800

no.of days=y/3y/800=800÷3=266.666666
Answered by Dhruv4886
0

a and b can complete the work in 266 2/3 days

Given:

Two workers a and b are employed for a cleanup work.

a can clean the whole area in 800 days.

a works for 100 days and leaves the work

b worked alone finishes the remaining work in 350 days

To find:

if a and b would have worked for the whole time, how much time would it have taken to complete the work?

Solution:

Given that a can clean the whole area in 800 days

⇒ The work can be done by a in 1 day = \frac{1}{800}  

a works for 100 days and leaves the work

⇒ the work done by a in 100 days = \frac{1}{800}(100) = \frac{1}{8}  

If a did 1/8th of work then remaining work that done by b =1-\frac{1}{8} = \frac{7}{8}  

given b completed \frac{7}{8} th of work in 350 days  

⇒ The work can be done by b in 1 day = \frac{ \frac{7}{8} }{350}  = \frac{7}{8} (\frac{1}{350}) = \frac{1}{400}  

If a and b worked together the work can be done in 1 day = \frac{1}{800} +\frac{1}{400} = \frac{3}{800}

⇒  \frac{3}{800} of the work can be done in 1 day

Number of days to complete 1 work = \frac{1}{\frac{3}{800} } (1) = \frac{800}{3} = 266 2/3 days    

a and b can complete the work in 266 2/3 days

#SPJ2

Similar questions