Two workers a and b are employed to do a cleanup work. a can clean the whole area in 800 days. he works for 100 days and leaves the work. b working alone finishes the remaining work in 350 days. if a and b would have worked for the whole time, how much time would it have taken to complete the work?
Answers
no.days a worked=100
remaining a=700
no.day to b=350
700a--------------------350b
800a--------------------x
x×700a=350b×800a
x=400
let total land =y
per one day a=y/800
per one day b=y/400
each day=(y/800)+(y/400)
=3y/800
no.of days=y/3y/800=800÷3=266.666666
a and b can complete the work in 266 2/3 days
Given:
Two workers a and b are employed for a cleanup work.
a can clean the whole area in 800 days.
a works for 100 days and leaves the work
b worked alone finishes the remaining work in 350 days
To find:
if a and b would have worked for the whole time, how much time would it have taken to complete the work?
Solution:
Given that a can clean the whole area in 800 days
⇒ The work can be done by a in 1 day =
a works for 100 days and leaves the work
⇒ the work done by a in 100 days = =
If a did 1/8th of work then remaining work that done by b =
given b completed th of work in 350 days
⇒ The work can be done by b in 1 day = = =
If a and b worked together the work can be done in 1 day = =
⇒ of the work can be done in 1 day
Number of days to complete 1 work = = 266 2/3 days
a and b can complete the work in 266 2/3 days
#SPJ2