two workers A and B together can finish a work in 8 days they worked together for 6 days and a left the work the remaining work was completed by b alone in 6 days how many days code each day take to complete the work individually
Answers
Answered by
2
Solution:-
Let A takes 'x' time to complete the work alone.
So, one day work of A = 1/x
And,
Let B takes 'y' time to complete the work alone.
So, one day work of B = 1/y
One day work of both A and B when they work together = 1/8
Now,
⇒ 1/x + 1/y = 1/8
They work together for 6 days and A left. That means 6/8 work had already been completed.
So, remaining work = 1 - 6/8
= 2/8
= 1/4
So, 1/4th part of total work is still remaining and B finished this 1/4th part in 6 days.
⇒ 6(1/y) = 1/4
⇒ 6/y = 1/4
⇒ y = 24
Hence B will take 24 days to complete the work alone.
Now,
Substituting the value of y = 24, we can have the value of x.
1/x + 1/y = 1/8
⇒ 1/x + 1/24 = 1/8
⇒ 1/x = 1/8 - 1/24
⇒ 1/x = 2/24
⇒ 1/x = 1/12
⇒ x = 12
So, A will take 12 days to complete the work alone.
insaneabhi:
please mark as brainliest
Answered by
0
Worker a completes work in x days
He will complete work in one day = 1/x
Women completes a work in y days
She will complete work in 1 day = 1/y
Together they complete work in 8 days
Then work in 1 day = 1/8
Form equation
1/x + 1/y = 1/8
Solve equation and get answer
He will complete work in one day = 1/x
Women completes a work in y days
She will complete work in 1 day = 1/y
Together they complete work in 8 days
Then work in 1 day = 1/8
Form equation
1/x + 1/y = 1/8
Solve equation and get answer
Similar questions