Math, asked by karansingh5935, 1 year ago

Two workers a and b working together completed a job in 7 days. If a worked thrice as efficiently as he actually did and b worked 1/3 as efficiently as he actually did, the work would have been completed in 3 days. A alone could complete the work in how many days?

Answers

Answered by kitty4846
7
Two workers A & B working together completed a job in 5 days. If A worked twice as efficiently as he actually did & B worked 1/3 as efficiently as he actually did, the work would have been completed in 3 days. When could A alone complete the work?

Answer

45

Follow

Request

More

6 ANSWERS



Louis M. Rappeport, PhD. Unicorn Wrangler

Answered Jun 8, 2018

According to the first part of the question:
1/A + 1/B=1/5
Then the second part says:
2/A +1/3B=1/3
So:
1/A=1/5–1/B
2/A=2/5–2/B
2/5 -2/B + 1/3B=1/3
6B-30+5=5B
B=25
1/5–1/25=4/25
A=1 / 4/25=25/4 days working alone

Answered by arshikhan8123
0

Concept:

In mathematics, there are different operation like addition, subtraction, multiplication and division.

Given:

A and B can together complete a work in 7 days.

Find:

Time taken by A to complete the work alone.

Solution:

Let:

total work= W.

The speed of A be x work/day.

The speed of B be y work/day.

Two workers A and B working together completed a job in 7 days.

This means:

W=7x+7y  ...(1)

Now, if A worked thrice as efficiently as he actually did and B worked 1/3 as efficiently as he actually did, then:

W= 9x+y

Multiplying 7 on both sides:

7W=63x+7y   ...(2)

Solving (1) and (2) we get,

6W=56x

W/x=56/6=28/3=9 (1/3) days

Therefore, A alone can complete the work in 9 (1/3) days.

#SPJ3

Similar questions