uncle 40 men can finish a piece of work in 6 days how many men will be needed to finish it in 16 days​

Answers

Answered by saroj9997
0

Answer:

15 men

Step-by-step explanation:

40 men = 6 days

x men = 16 days

x=40*6/16

x=240/16

x=15

Hence 15 men are required to finish work in 16 days

HOPE IT HELPS YOU

Answered by panchbhaiharish2
0

Answer:

15

Step-by-step explanation:

40 men finish it in =6 days

then...

in 1 Day men required = 40 × 6

  • 40 × 6 = 240

then...

in 16 days men required = 240 ÷16

  • 240 ÷ 16 = 15

Hence.., 15 men will be needed to finish it in 16 days