uncle 40 men can finish a piece of work in 6 days how many men will be needed to finish it in 16 days
Answers
Answered by
0
Answer:
15 men
Step-by-step explanation:
6 days need = 40 men
1 day will need = 40×6 men
16 days will need = (40×6)/16
= 240/16
= 15 men