Under ______ production a single assignment is undertaken
Answers
Answered by
1
Answer:
Project production
Explanation:
May be I think it is wrong
Answered by
0
Answer:
Under project production a single assignment is undertaken
Explanation:
- Project production is characterized by complex sets of activities that must be performed in a particular order within the given period and within the estimated expenditure.
- Where output of a project is a product, such products are generally characterized by immobility during transformation.
- Operations of such products are carried out in “fixed position assembly type of layout” which can be observed in production of ships, locomotive and aircraft, construction of roads, buildings, etc.
- Requirement of resources for project production is not uniform. At the end of the project, resources from the project are redeployed elsewhere in other projects. Even during the life of the project, requirement of resources is not uniform.
- A project generally involves many tasks, each having its own specialization to be performed by different agencies. The tasks generally have strict precedence amid as such co-ordination between agencies is of utmost importance.