The Menlyn Maine Central Square project comprises a 7 storey office block, a large retail section with all the major anchor tenants, including Pick & Pay, Spar and a Virgin Active, as well as a 5 storey hotel, all constructed on a super basement 3 levels deep with a total basement area of approximately 90,000 m2. The project will aim to achieve a four star Greenstar rating making it part of the largest green precinct in Africa. The estimated contract value is R 950 million and construction will take place over a single phase spanning 30 months. The project has kicked off with bulk earthworks, with an estimated total of 220 000 m3 of soil and rock to be removed. The total estimated structural concrete on the project is in the region of 65,000 m3, peaking at about 1 350 m3 per week.

Contract Duration: Jan 2014 - Nov 2016

Contract Value: ZAR 950 Million

Engineers: WSP Consulting Engineers