A work can be done in 25 days
by 8 men working together. If after !
5 days of work they are joined by
2 others, in how many days will the
remaining work be finished?​

Answers

Answered by ramashishgupta8161
0

Answer:

hey mate here is your answer

thanx for asking a question

Attachments:
Answered by zaidazmi8442
2

A man can finish a work =200 days

A man do work in one day =1/200

8 men can do work in one day=1/25

8 men do work in 5 days=1/5

remaining work =4/5

10 person can do work in one days=1/20

10 person finished remaining work =(4/5)×20=16days


zaidazmi8442: mark as brain list plz