Computer Science, asked by atlabhaskar245, 6 months ago

Use Johnson rule to assign the tasks in two machines. The correct sequence is?
Processing time
Machine 1 Machine 2
Job
A
12
15
B
4
3
C с
8
D
20
Olao
E
7
F
9
a) EBDCFA
b) EBCFDA
c) EDCFAB
d) None of the above​

Answers

Answered by asrith18
4

Answer:

I think it is option (b)