Use Johnson rule to assign the tasks in two machines. The correct sequence is?
Processing time
Machine 1 Machine 2
Job
A
12
15
B
4
3
C с
8
D
20
Olao
E
7
F
9
a) EBDCFA
b) EBCFDA
c) EDCFAB
d) None of the above
Answers
Answered by
4
Answer:
I think it is option (b)