Math, asked by swetha2039, 8 months ago

v) A alone can do a piece of work in 35 days. If B is 40% more effi cient than A, then B will fi nish the work in ___________days.

Answers

Answered by kuldeep20941
0

=====================================

Given :-

1. A finish the work in 35 days

2. B is 40% more efficient than A

To Find :-

In how many days B will finish the work?

Solution :-

It is given that B is finishing the work with 40% more efficiency . it means B will finish the work first.

less time taken by B than A = 40% Of time taken by A

= 40/100 × 35 = > 14 Days.

Time taken by B = 35 - 14 = 21 days

=====================================

Similar questions