v) A alone can do a piece of work in 35 days. If B is 40% more effi cient than A, then B will fi nish the work in ___________days.

Answers

Answered by sprakher1
0

Answer:

49 days

Step-by-step explanation:

= let total work of A = 100 units

= A can complete 100 units in = 35 days

= since B is 40% more efficient

= B can complete 140 units in = 35 days

= B can complete 100 units in = 35 × 140 ÷ 100

= B can complete 100 units in 49 days