V can complete a work in 15 days and S can complete the same work in 10 days, in last 5 days V left the work and S complete the remaining alone. Find the number of days in which S and V worked together
Answers
Answered by
1
Answer:
Given, A and B can complete a work in 15 days and 10 days respectively.
Step-by-step explanation:
=> The amount of work done by them together in 1 day = 1/15 + 1/10
= (2+3)/30 = 5/30 = 1/6
Given, they worked together for 2 days.
=> The amount of work done by them together = 2*(1/6) = 1/3
The amount of work to be completed by A alone = 1 - 1/3 = 2/3
The number of days taken by A alone to complete the remaining work = (2/3)/(1/15) = 30/3 = 10
=> The whole work was completed in (2+10) i.e., 12 days.