Venkat can do a piece of work in 20 days whereas Shyam can do the same piece of work in 15 days.
They started the work together but Shyam quits after 5 days. If they are paid Rs. 3000 for this job, find
Shyam's share.
Rs. 800
O
Rs. 2000
O
None of these
Rs.1000
С​

Answers

Answered by rahulkumarr179
1

Answer:

in 5 days shyam would do 1/3 work for full work is gets 3000.

for 1/3 he gets,

1/3×3000=1000

so ,he will 1000 rupees.

hope it helps u dear ☺️☺️☺️