Vicky can finish the work in 10 days, bala can finish the work in 12 days, and venkat can finish the work in 15 days. They all start to work together. Vicky leaves the work after two days and bala leaves 3 days before the work was completed. How long did it take for the work to be completed?
Answers
Answer:
13
Step-by-step explanation:
The answer is 6 days
Given: Vicky can finish the work in 10 days
Bala can finish the work in 12 days
Venkat can finish the work in 15 days
They all started the work together
Vicky leaves the work after 2 days
Bala leaves the work before completing 3 days
To find: How many days it will take to complete the work
Solution:
From given data
Vicky can finish the work in 10 days
⇒ the work can be done by Vicky in 1 day = 1/10
Bala can finish the work in 12 days
⇒ the work can be done by Bala in 1 day = 1/12
Venkat can finish the work in 15 days
⇒ the work can be done by Venkat in 1 day = 1/15
⇒ the work can be done by them together in 1 day =
=
They all started the work together and Vicky leaves the work after 2 days
which means they worked together for two days
⇒ the work can be done in 2 days = =
After that Venkat and Bala worked together
Assume Bala and Venkat worked for x days
⇒ then the work done by Bala and venkat in x days =
Bala leaves the work before completing 3 days which means last 3 days work is done by Venkata
⇒ the work done by Venkata in 3 days = =
Here, the total work = 2 days work + x days work + 3 days
⇒ = + + = 1
⇒ = 1
⇒ 12+ 12x + 6 = 30
⇒ 12x = 30 -18
⇒ 12x = 12
⇒ x = 1
⇒ Bala and Venkat worked for 1 days
The number of days to complete the work = 2 + 1 + 3 = 6 days
Therefore, the number of days to complete the work = 6 days
#SPJ2