vijay can complete his project in 35 days what part of the project will be completed in 5 days
Answers
Answered by
1
Answer:
7
Step-by-step explanation:
part of work completed in 5 days = 35÷5
Answered by
2
Answer:
1/7 th part
Step-by-step explanation:
35 days - 1 whole
1 day - 1/35 part
5 days - (1*5)/35 parts
=1/7 th part