Math, asked by mgasoverse20, 6 months ago

Vikas and Monu can do a work in 4 and 12 days respectively they work together for a few days and after which Vikas leaves and Monu complete the remaining after how many days Vikas left


plzzzz tell​

Answers

Answered by nagulavanchathirupat
1

Answer:

10 Men begin work

It could been done in 40 days.

Let 4 men left after x days.

Left days are 40−x if they do not left and 50−x if they left.

(40−x)10=(50−x)6

400−10x=300−6x

1000=4x

x=25 days. please mark me as brainleast answr

Similar questions