Vitin can do a piece of work in 24 days while Raman can do it in 30 days. In how
many days can they complete it, if they work together?
Answers
Answered by
4
Answer:
Vitin can in 24 days finish the full work i.e 100% or 1 of it.
∴ Vitin can in 1 day finish 1/24th of the work.
Raman can in 30 days finish the full work i.e 100% or 1 of it.
∴ Raman can in 1 day finish 1/30th of the work.
Therefore amount of work both of them can do in 1 day
= 1/24+1/30
= 24+30/720
= 54/720
= 3/40
Therefore time taken by them = 1/(3/40) = 40/3 = 13
1/3 days