vrujesh takes 6 days less to complete one work then Kaushal if Kaushal and vrujesh work together they can finish the work in 4 days in how many days Kaushal can alone finish the work
Answers
If both can together work in 4 days and Vrujesh takes 6 days less than Kaushal when wroking alone, then Kaushal can alone finish the work in 12 days.
Step-by-step explanation:
Let's assume that Kaushal alone takes "x" days to finish one work, then Vrujesh alone would finish the same work in "(x-6)" days.
So,
Work done by Kaushal in 1 day =
Work done by Vrujesh in 1 day =
It is also given that Kaushal and Vrujesh together can finish a work in 4 days
So, work done by Kaushal & Vrujesh together in 1-day =
Now, we can write the eq. as,
[Kaushal's one day's work] + [Vrujesh's one day's work] = [(Kaushal + Vrujesh)'s one day's work ]
⇒
⇒
⇒ 8x - 24 = x² - 6x
⇒ x² - 14x + 24 = 0
⇒ x² - 12x - 2x + 24 = 0
⇒ x(x - 12) - 2(x - 12) = 0
⇒ (x - 12)(x - 2) = 0
⇒ x = 12 or 2
(If we take x = 2 days then Vrujesh will take 2-6 = -4 days, which is completely meaningless)
∴ x = 12 days
Thus, Kaushal can alone finish the work in 12 days.
-------------------------------------------------------------------------------------------
Also View:
A and B working together can do a work in 6 days. if A takes 5 days less than B to finish the work in how many days B alone can do the work ?
https://brainly.in/question/8587762
Manish takes 9 days more than his father to do a certain piece of work together they can do the work in 6 days •how many days will Manish take to do that work alone?
https://brainly.in/question/14532722
Answer:
hope u like it
Step-by-step explanation:
this is your answer....