A and B can complete the work individually in 24 days and 30 days
respectively, working 10 hours a day. Work is to be done in two shift.
Morning shift lasts for 6 hours and evening shift lasts for 4 hours. On
the first day A works in the morning shift while B works in the evening
shift. Next day A works in the evening shift while B works in the
morning shift and so on. It means they work alternatively with respect
to their shifts. Thus they work on this pattern till the work is completed.
On which day the work got completed?