Math, asked by agrawaltanya438, 2 months ago

W salle distance at a speed of 36 km/h?
how many days will the remaining work be finished?
7. A contractor employed 210 men to built a house in 60 days. After 12 days, he was joined by 70 more men
8. 1200 soldiers in a fort had enough food for 28 days. After 4 days some soldiers were transferred to another
and thus the food lashed for an extra 32 days. How many soldiers left the fort?​

Answers

Answered by ItzMeMukku
0

Step-by-step explanation:

7. After 12 days, 70 more men joined. Now, 280 men can finish the work in 210×48280 days = 36 days. Hence, it will take 36 days to finish the remaining work.

8. 1200 soldiers in a fort had enough food for 28 days. After 4 days, some soldiers were sent to another fort and thus the food lasted for 32 more days. ... The number of soldiers who were sent to another fort lasted for 4 days in this fort. So the number of days left for enough food = (28 – 4) = 24 days.

Answered by SweetestBitter
0

QUESTION :

A contractor employed 210 men to built a house in 60 days. After 12 days, he was joined by 70 more men.

ANSWER :

After 12 days, 70 more men joined.

Now,

280 men can finish the work in

210×48/280 days = 36 days.

Hence, it will take 36 days to finish the remaining work.

FINAL ANSWER : 36 Days

Similar questions