Math, asked by soumyadip26062006, 20 days ago

watering the garden? Mason A can build a shed in 12 hours. Mason B takes 9 hours while Mason C takes 12 hours to do the same job. If the three masons are put to work together how long will they take to build the shed? How will the payment of 1000 for the job be distributed among the three?​

Answers

Answered by vishalns1994
0

Answer:

All three A,B,C take 3.6 hrs to build the shed.

Payment : A - 363.6, B- 272.8, C- 363.6

Step-by-step explanation:

Given : Mason A takes 12 hrs to build a shed

            Mason B takes 9 hrs to build a shed

            Mason C takes 12 hrs to build a shed

            Payment for the total job = 1000

Solution :

1. In one hr A finishes = 1/12 of shed

                    B finishes = 1/9 of shed

                    C finishes = 1/12 of shed

             If all together work = 1/12 + 1/9 + 1/12

                                             = 10/36 of shed

∴   10/36 of shed work takes 1 hr

        1 shed work = 1 *36/10

                             = 3.6 hrs

2. Payment of 1000 distribution A:B:C = 12 : 9 : 12

    A payment = 1000* 12/33

                       = 363.6

   B payment = 1000 * 9/33

                      =  272.8

   C payment = 1000* 12/33

                       = 363.6

       