Geography, asked by sushmitadorjee, 7 months ago

what are the causes of production of thermal power production in East India ?​

Answers

Answered by abhipatel8119
3

Answer:

India's electricity sector consumes about 72% of the coal produced in the country. For utility power generation, India consumed 622.22 million tons of coal during 2019-20 which is less by 1% compared to 628.94 million tons during 2018-19. However coal imports for utility power generation increased by 12.3% during year 2019-20 at 69.22 million tons from 61.66 million tons during 2018-19.[76] A large part of the Indian coal reserve is similar to Gondwana coal: it is of low calorific value and high ash content, with poor fuel value. On average, Indian coal has a gross calorific value (GCV) of about 4500 Kcal/kg, whereas in Australia, for example, the GCV is about 6500 Kcal/kg .[77] The result is that Indian power plants using India's coal supply consume about 0.7 kg of coal per kWh of power generation, whereas in the United States thermal power plants consume about 0.45 kg of coal per kWh. In 2017, India imported nearly 130 Mtoe (nearly 200 million tons) of steam coal and coking coal, 29% of total consumption, to meet the demand in electricity, cement and steel production.[8][78]

The Centre for Science and Environment has assessed the Indian coal-based power sector as one of the most resource-wasteful and polluting sectors in the world, in part due to the high ash content in India's coal.[79] India's Ministry of Environment and Forests has therefore mandated the use of coals whose ash content has been reduced to 34% (or lower) in power plants in urban, ecologically sensitive and other critically polluted areas. The coal ash reduction industry has grown rapidly in India, with current capacity topping 90 megatonnes.[when?][citation needed]

Before a thermal power plant is approved for construction and commissioning in India it must undergo an extensive review process that includes environmental impact assessment.[80] The Ministry of Environment and Forests has produced a technical guidance manual to help project proposers avoid environmental pollution from thermal power plants.[81] As of 2016, the existing coal-fired power stations in the utility and captive power sectors were estimated to require nearly 12.5 million INR per MW capacity to install pollution control equipment to comply with the latest emission norms set out by the Ministry of Environment and Forests.[82][83][84][85] In April 2020, CPCB declared that over 42,000 MW thermal power plants have outlived their lives.[86] India has also banned imports of pet coke for use as fuel.[87] As a signatory to the Paris Agreement, India is also reducing power generation from coal to control the emission of greenhouse gases.[88]

The state and central power generation companies are permitted by the Government of India to minimize the cost of coal transportation using flexible coal linkage swaps from inefficient plants to efficient plants, and from plants situated far from coal mines to plants close to the pit head, leading to a reduction in the cost of power.[89] Although coal imports for consumption in the utility sector are declining, the overall imports of steam coal are increasing as the local coal production is unable to meet the requirements of coal-fired captive power plants.[90][91]

Natural gas supply constraints Edit

See also: List of power stations in India § Gas or Liquid Fuel Based

The installed capacity of natural gas-based power plants (including the plants ready to be commissioned with the commencement of natural gas supply) was nearly 26,765 MW at the end of the financial year 2014-15. These plants were operating at overall plant load factor (PLF) of 22% due to a severe shortage of natural gas in the country,[92] and the fact that imported liquid natural gas (LNG) was too expensive for power generation. Many power stations were shut down throughout the year for lack of natural gas supply. The natural gas shortage for power sector alone was nearly 100 million cubic metre per day at standard conditions.[93] The break-even price for switching from imported coal to LNG in electricity generation was estimated to be approximately US$6 per million British thermal units ($20/MWh) (themal energy).[94] The Indian government has taken steps to enhance power generation from gas-based power plants by waiving import duties and taxes.[95][96]

Answered by vishwas192
0

Answer:

I was reading a hindi chapter name chapter 4 pehli chuk class 7th but there are some words which i didn't understand could please tell me the meaning of underlined words..

Similar questions