What are the steps involved in critical path method as a part of project scheduling?
Answers
Answered by
0
Answer:
Critical path method (CPM) is a resource-utilization algorithm for scheduling a set of project activities.
The steps involved in critical path method as a part of project scheduling :-
- Specify the individual activities.
- Determine the sequence of those activities.
- Draw a network diagram.
- Estimate the completion time for each activity.
- Identify the critical path (the longest path through the network).
- Update the CPM diagram as the project progresses.
Hope it helps! ! !