What do I need to consider when thinking about communicating CM status?
A) The project's development stage and the level of CM risk
B) The project's duration and level of CM risk
C) The project's development stage and network connectivity
D) The project's duration and development stage
Answers
Answered by
6
Answer:
A) The projects development stage and the level of CM risk
Answered by
3
Answer:
Option 1 - the project's development stage and the level of CM risk