What is nervousness in material requirement planning (mrp) system?
Answers
Answer:
In practice, material planning is usually conducted using MRP systems. Up to
now, the use of alternative concepts such as LRP or FiRST is not widespread.
Consequently, the analysis of nervousness in MRP systems is the main focus
in literature and in the subsequent analysis.
In literature, MRP nervousness is defined in several ways. In an early work,
Steele [124] defines a "nervous MRP" system as one that causes excessive
changes to low-level requirements when the master schedule is not changed
significantly. He identifies the following reasons for nervousness in MRP systems.
• Master schedule changes/Unplanned demand:
Rescheduling the MPS, in general, leads to replanning activities on lowlevel items. Because of lot-sizing, even minor time-phasing changes on the
MPS level may lead to major rescheduling actions on lower stages. In particular, changes in lot sizes on the MPS level may cause rescheduling of
released orders at lower levels (see also Mather [86]).
• Allocation not issued in expected quantity: (or contrary to the plan, Type
I)
The difference between the actual demand and expected (planned) demand
of a component may lead to changes in the due date of the replenishment
requirement. An allocation gives the planned issue for a shop requirement,
and if it is not available in the expected quantity, then the forecasted runout date will shift. Similar problems occur if a machine break down, or
a supplier cannot deliver the material for a component in time1 . Then,
assemblies on which these components are used must be delayed (see, e.g.,
Mather [86]).
• Order released in unplanned quantity: (or contrary to the plan, Type II)
The impact of this is the same as for type I, i.e. subordinate requirements
will again jump forward, but in this case, all components are influenced.
The same holds for unexpected scrap which causes planned orders to be
needed earlier (see, e.g., Mather [86]).