What is the amount of water required
for a workable RC of mix 1: 2:4 by
weight when w/c ratio is 0.60 and
unit weight of concrete is
2,400 kg/m3.
(A) 165 L
(B) 205 L
(C) 245 L
(D) 285 L
Answers
Answered by
0
The total water required in the mixture is 206 litres .
Explanation:
- The total quantity of cement in 1 m^3 concrete is 2400/7 = 343 kg
- Now, your water cement ratio is 0.6
- Now multiply the quantity of cement by the water cement ratio
343 x 0.6= 206 kg of water.
As we know that 1 kg of water is equal to 1 litre
Therefore,\
206 Kg = 206 Litres
Thus the total water required in desired mixture is 206 litres .
Also learn more
Milk in in a container which is in the form of a frustum of a cone of height 30 cm and the radius of whose lower and upper circular ends are 20 cm and 40 cm respectively is to be distributed in a camp for flood victims if this milk is available @ rupees 30 per litre and 880 litre of milk is needed for a camp find how many such containers of milk are needed for a camp and what cost will it put on the donor agency for this ?