Math, asked by deepaoli717, 7 months ago

what is the complete ment of45°​

Answers

Answered by Ameya09
0

Answer:

45 men can finish a job in =16 days

after 6 days the situation is

45 men can finish a job in =16–6=10 days

1 man can finish this job in =10×45=450 days

since 30 more men join in so now

45 +30=75 men can finish the job in =450/75=6 days.

15.7K viewsView 39 Upvoters

Vijaya Shelar, B.E from Shivaji University (2020)

Answered April 17, 2020

45 men 1 day work is … 1/16

45 men work for 6 days ..… 1/16=3/8 work done

1-3/8 = 5/8 … work left

After 6 days 30 men join …..total men=75 men

if 45 men 1 day work is 1/16… then 75 men 1 day work will be 5/48 (perform cross multiplication)

X=days to complete remaining work 5/48 * x=5/8

X= 6 days

1.1K viewsView 3 Upvoters

Sponsored by Nokia

The best moments are waiting to be captured.

Capture stunning views with an incredible quad camera and AI imaging. Be amazed by Nokia 5.3.

Geetesh Sehrawat, former In Pursuit to Clear SSC CGL 2018

Answered August 24, 2018

When the new men are added the old are still working. A vital point that people ignore generally that changes the equation.

10.1K viewsView 56 Upvoters

Related Questions

More Answers Below

12 men can complete a work in 90 days. 30 days after they started work, 2 men left and 8 men joined. How many days will it take to complete the remaining work?

If 45 men can complete a project in 30 days while working 12 hours a day, in how many days can 60 men do the project if they work 10 hours a day?

If men completed work in 3 days, how many days would 5 women take?

Twenty men can do a certain work in 18 days. After 3 days of starting, 5 men joined them. How many days can the remaining work be completed?

A completes a work in 12 days. B completes in 15 days. A started working alone and after 3 days B joined him. How many days will they now together take to complete the remaining work?

Bryan Wijaya, studied Maths and Programming at High Schools (2018)

Answered January 14, 2019 · Author has 738 answers and 255.8K answer views

Let the number of men be m, work be w, and days be d.

m : w : d

45 : 1 : 16

Logic: less days = less work

m : w : d

45 : 1 : 16

45 : 1/16 : 1

The rate of 45 men is (1/16) works per day.

After 6 days:

Works completed: (1/16) x 6 = 3/8

Works left: 1 - (3/8) = 5/8

30 more men join them:

Men: 45 + 30 = 75

1 Man's rate = (1/16)/45 = 1/720

75 Men's rate = (1/720) x 75 = 15/144

Time to complete remaining work:

(5/8)/(15/144)

= 6 days

2.5K viewsView 2 Upvoters

Ramesh Sabhnani

Answered August 24, 2018 · Author has 306 answers and 92K answer views

4.6K viewsView 25 Upvoters

Sponsored by BYJU'S Classes for JEE

Online JEE classroom program by BYJU'S classes.

Regular classes, India's best teachers, live doubt solving, All India Test Series, daily practice probs.

Hungenahalli Sitaramarao Badarinath, former CE, Graduate, PG, Research Scholar and Faculty at Indian Institute of Technology, Roorkee (1964-2000)

Answered August 24, 2018 · Author has 27.4K answers and 14.5M answer views

The work requires 45x16 = 720 worker-days.

In the first 6 days the work completed is the equivalent of 45x6 = 270 worker-days.

What remains to be done after the first 6 days = 720=270 = 450 worker-days..

Now the 450 worker-days of work can be completed by (45+30 = 75) 75 workers in 450 worker-days/75 workers = 6 days.

2.5K viewsView 6 Upvoters

Ritika Jain, Philanthropist, Bibliophile & an Upcoming Entrepreneur

Answered May 28, 2019 · Author has 249 answers and 26.4K answer views

Men = 45

Days = 16

Total Work = 720 Units

6 days work = 45 * 6 = 270 units

Remaining = 720 - 270 = 450 units

Men = 30 + 45 = 75 men

work = 450

Time = 450/75 = 6 days

Total Time taken will be 12 days

?

Step-by-step explanation:

Answered by gandiharini2007
1

Answer:

45°

Step-by-step explanation:

complementory of 45°=90°-45°=45°