What is the repeatable chunk of time on which agile scheduling and planning depends?
Answers
Answered by
0
The answer is timebox.
The repeatable chunk of time on which Agile scheduling and planning depends is called timebox. The time scheduled for an activity cannot go beyond the time limit specified in the timebox. The activity must come to an end by the time specified in its timebox is over. Thus, all activities in an Agile project are split into various timeboxes.
Answered by
4
Hello mate
here's your answer
_________________
Time box is the repeatable chunk of time on which agile scheduling and planning depends.
________________
Thanks
here's your answer
_________________
Time box is the repeatable chunk of time on which agile scheduling and planning depends.
________________
Thanks