What is the right time to deploy the Defect Prediction model for a Development project?
a) After delivering to the Customer
b)After go-live
c)At the start of the project
d)Mid way through the project execution Submit
Answers
Answered by
4
Answer:
At the start of the project
Explanation:
UCX48Lo9mbeVVeiNJF1ZVOOA by the way please visit to my channel like and subscribe it
Answered by
0
Explanation:
Among the various options given in question statement the correct option is the third one that is at the start of the project. in Defect Prediction model, we are able to identify the possible defects in the system and if these defects are addressed at the beginning of the project, then we can save alot of time and resources and eventually this will lead to a fool proof design of the system
Similar questions
Chemistry,
14 days ago
Hindi,
14 days ago
English,
14 days ago
Chemistry,
29 days ago
Math,
29 days ago
Math,
8 months ago
Computer Science,
8 months ago
Social Sciences,
8 months ago